Tuesday, July 8, 2008
Wednesday night 'finish-up' work session
Anyone who has tools left over at THGB needs to pick them up soon as we need to return the construction trailer. Also, please double-check that any tools you brought home are yours. We have some tools that are missing but lots that are still on-site.
We plan on starting our work at 6 pm and working until about 8 pm. Hope to see you then.
Saturday, June 14, 2008
Pictures of The House God Built
Friday, June 13, 2008
Dedication Day
We've asked for your help to build this house and many have answered above and beyond that call. We now ask for your help in it's dedication. Please come celebrate with us at 10 am. Following the program there will be tours of the first floor of the house and a BBQ afterwards. It should be an awesome day.
The House God Built is at 529 S. Hanover. We recommend parking on College which can be accessed from West End near it's intersection with Highway 74.
Just because construction is done doesn't mean that the blog is ending. We will be uploading pictures of the last phases of construction and dedication soon.
View Larger Map
Last day of construction set for Friday
Friday will be another marathon day to complete construction. Work will resume at 8 am and continue late into the night. We still have projects that are being completed and are working through these quickly. Also we have two critical inspections scheduled today so please be in prayer for The House God Built as we work through this last day.
Please come for the dedication on Saturday at 10 am. We're expecting a big crowd and would love it if you could be a part of it. Following the dedication will be tours of the house and lunch. Parking is limited so please carpool if possible and the best parking will be on College. For directions see the map on yesterday's posting below.
Thursday, June 12, 2008
Thursday and Friday plans
Plans are also coming together for the dedication on Saturday. Please join us at 10 am to celebrate what God has done and is doing in Cape Girardeau. Following the dedication we will have tours of the house and lunch is provided at noon.
Hanover is a rather narrow street and parking is limited. We want your entire family to come but please come in one car if possible. We also suggest parking on College and walking up to THGB. Hope to see you Saturday!
View Larger Map
Wednesday, June 11, 2008
Tuesday update and plans for the week
Tuesday, June 10, 2008
Tuesday plans
Monday, June 9, 2008
Monday night work and Tuesday plans
Tuesday will be an all day work session to finish up as many items as possible. More information regarding Tuesday will be posted later today.
Sunday, June 8, 2008
Another great weekend comes to a close
Inside, the stair railing continues to go up. Lots of cleaning and arranging happened inside THGB also. Because of this the house is now closed to visitors and will only be open to those who are working inside the house. It will be open again on Saturday to walk through during the dedication.
Until Saturday we'll be working at the house every evening starting at 6 pm. Tuesday we are planning to have a big push to finish up many of the last minute details and we will be working most all day. Please come help that day or any evening if you have the opportunity.
Great progress on Saturday, more planned for today
Saturday, June 7, 2008
Last weekend of work at The House God Built -UPDATED
Friday, June 6, 2008
Thursday update and weekend plans
Thursday, June 5, 2008
Wednesday progress and Thursday plans
Our plans to lay brick on the driveway tonight have been postponed. We will continue to finish up tasks inside THGB to be able to turn rooms over to the decorating team as soon as possible. Tonight we will continue with paint touch-ups and hopefully be able to install the last of the interior doors and trim. We also will continue with the stair railing installation. If you are able to help please come on over. We'll start working at about 6 pm.
Wednesday, June 4, 2008
Tuesday update and plans for the week
Tuesday, June 3, 2008
Concrete update
Concrete is on the way
Monday, June 2, 2008
Less than two weeks to finish The House God Built
The remainder of the doors and trim are scheduled to be availalbe on Wednesday as is the remaining appliance. We are expecting a big push this week to see this project through to completion. Check back often for updates.
Friday, May 30, 2008
Time's running out to help
Inside we are finishing up! We will have plumbers setting fixtures this weekend and carpenters finishing the door and trim installation. We need experienced painters to help patch some damaged paint on the ceilings and to help with a touch-ups around the house once the remaining carpentry and plumbing work is finished. We also need to seal grout on all tile floors and remove all remaining tools and materials that are no longer needed at the house.
We would love to have your help. Please consider coming over to help this weekend if you can. We'll start working on Saturday at 8 am and will continue until at least 5 pm. We also plan on working Sunday after 1 pm. You can sign-up to help online or give us a call at 573-837-4047 with any questions.
Wednesday, May 28, 2008
Wednesday update
The doors and trim that were anticipated today were not available so that has been delayed. Hopefully they will be available no later than this weekend. Speaking of this weekend we still need to finish the remaining doors and trim, place rock on the fireplace, seal grout, and set plumbing fixtures.
If you would like to help out watch for more information here on the blog or sign-up online at our volunteer site. If you have any questions or would like to donate to The House God Built please give us a call at 573-837-4047.
Tuesday, May 27, 2008
Tuesday update and plans
Tonight we'll be working on some miscellaneous items inside the house. We can install the toe kick and crown molding on the cabinets, install door hardware, and do some clean-up. With all of the people working at the house today and the muddy conditions outside it is more than ready for a little TLC.
On Wednesday the remainder of the doors and trim will be ready for us to pick up and install. If this can be done during the day we can finish the installation tomorrow night. The blog will be updated once we know that we'll have materials ready.
One final thought for today - I've gotten lots of questions on why there have not been many pictures lately to show the progress. The answer is that we are keeping the interior of the house a suprise for Pastor Thomas and his wife. They will see the inside of the house for the first time at the dedication on June 14th.
Weekend progress and plans for the week
We also received word of donations of the remaining kitchen appliances and landscaping!
This week should be another big week for things to start pulling together. The countertops are scheduled to be delivered and installed today which will allow us to proceed with the plumbing trim out. We also are expecting the air conditioning units to be installed this week.
In other good news there is a complimentary editorial in today's Southeast Missourian. You may read it online.
We'll be deciding on evening work plans as soon as we know that the materials will be available. Check back soon for updated information about our progress and plans.
Saturday, May 24, 2008
Saturday update
Inside we now have most of the interior doors on the first floor hung. Much of the trim was also installed on the first floor.
We'll meet at THGB on Sunday afternoon at 1 pm to work on the tasks listed below in yesterday's post that are still incomplete. If you have time to help we would love to see you at The House God Built.
Friday, May 23, 2008
Weekend plans
This weekend we have many things planned and would love to finish all of them and more if possible. With the extra day on Monday we are optimistic that these are all possible to complete with your help.
- Install toilets and tub fixtures. Countertops have been delayed until Tuesday so sinks will have to wait until next week.
- Cut up some brush that remains on the back of the property near the alley and haul it off next week.
- Ventilate the attic over the porch into the second floor attic.
- Install remaining doors and trim on first floor.
- Set stones on fireplace.
- Level driveway.
- Finish framing driveway.
- Start sculpting the soil to it's final condition prior to seeding.
- Finish back retaining wall.
- Repair driveway retaining wall.
We appreciate all of the help we've had so far with this amazing project and with a little more help we can see this through to completion soon. Besides physically helping with construction we can still use your prayers and donations. If you would like to help out please give us a call at 837-4047 or stop in to see us this weekend.
We'll be working on Saturday from 8 am until we're too tired to continue any longer. Lunch will be provided at noon. On Sunday we'll start working at about 1 pm and again work until we can't go any longer. We'll decide Monday's schedule based on how much we get accomplished on Saturday and Sunday. Hope to see you this weekend!
Doors and trim are going in.
Thursday, May 22, 2008
Grouting begins
Friday should be an exciting day as our countertops are scheduled to arrive. We are also expecting some of the interior doors and trim on Friday. Our plans are to meet at 6 pm and continue grouting both bathrooms.
Plans for this weekend are still developing but it is looking unlikely that it will include pouring concrete. Look for detailed weekend plans on the blog soon.
Wednesday, May 21, 2008
Tuesday/Wednesday updates and Thursday work sessions
We will be working Thursday at 10 am and again at about 6 pm. The morning session will be spent cleaning excess thinset from between tile in the bathrooms and laundry room. There may be some work on the retaining wall out back as well. The evening work session will be spent grouting tile. We would appreciate your help if you can find the time.
Tuesday, May 20, 2008
Tuesday work session
Monday, May 19, 2008
Article in the Southeast Missourian
You can't miss the article as it is on the front page (above the fold!) or you can view it on the seMissourian.com website.
As always, if you would like to be involved with The House God Built you can sign-up to help online or by calling our info line at 573-837-4047. Immediate needs are for people experienced (or willing to become experienced) with pouring concrete, installing doors and trim, grouting tile, and building a retaining wall.
We also are still seeking donations of new or gently used appliances (black or stainless would match the range hood/microwave combo and dishwasher that we already have been given), furniture, and household items. If you feel led to provide one or more of these items please contact us on the info line number above or by email at info@thehouseGodbuilt.com.
Sunday, May 18, 2008
Sunday update and plans for the week
In addition to the concrete pour we have plenty of other items planned soon at The House God Built. On Monday evening we will likely do a bit more work on the backyard with the backhoe and we would also like to grout tile. That would allow us to seal the grout on Wednesday and then install doors and trim soon afterwards.
This weekend we will be doing landsculpting. I'm not sure if that's a word but it describes our plans pretty well as we need to sculpt the terrain to it's final shape, finish installing a retaining wall in the backyard, and generally get the property ready for more traditional landscaping plans the following week. You can help by coming on Saturday anytime between 8 am and 8 pm or Sunday from 1 pm until 8 pm. You can sign-up to help online or by calling our info line at 837-4047. Watch the blog for more specific plans for days and times.
Saturday progress and Sunday plans
Today we'll continue working outside on framing the remainder of the sidewalks and driveway. We also need to form and pour the curbs and a pad for the air conditioning units today. We'll also install the last bit of the gutter drains and back fill trenches. Our hope is to pour the driveway, sidewalks and new basement floor this week.
We would love to have your help with these plans. Stop by today or check back on the blog for updated information on when we'll be working this week at The House God Built.
Friday, May 16, 2008
Weekend plans
Installing doors and trim
Grouting tile
Finish building the fireplace
Touch-up paint on walls and ceilings
Complete the porch railing
Build retaining wall in the backyard
Prepare the driveway and sidewalks for pouring concrete
As you can see, there is still lots to do for people of pretty much any skill level. We would love to have your help this weekend. If possible, sign-up online or call our info line to let us know how many people to expect.
Thursday, May 15, 2008
Siding is FINISHED!!
We're working on our plans for the weekend and would love you to be a part of them. You can sign-up to volunteer online or by calling us at 837-4047. There will be more information about our weekend plans posted here by tomorrow.
Wednesday, May 14, 2008
We have power!
Tuesday, May 13, 2008
One retaining wall in, one to go
Inside THGB the wood flooring is nearly complete and electricians were busy wiring up the service panel and installing fixtures and receptacles. We are hoping for AmerenUE to establish our service any day now.
This morning there will be a group in the house doing final paint touch-ups. Also we would like to have the concrete pad formed and poured for the air conditioning units done today. If you would like to help please stop by this morning.
Monday, May 12, 2008
Sunday update and Monday plans
Also, the wood floors should be completed later today. The installers arrived this morning with the remainder of the flooring and were getting set to start.
Check back on the blog later to find out how you can help out this week at The House God Built.
Saturday, May 10, 2008
Siding's nearly finished
We also were able to level the ground for pouring both sidewalks, moved the dumpster and the portapotty, and cleaned off the front of the property. Tomorrow we'll prep the driveway for concrete and begin laying the retaining wall.
If you're able to help we'll start working at about 1 pm on Sunday. We plan on working most evenings this week and will have times posted soon.
Timing is everything...
Our plan is to continue our pace of construction on the items unaffected by material delays. We still need your help though. Sign-up to help online or by calling our info line at info@thehouseGodbuilt.com. New workdays will be posted soon.
Weekend plans
It's a lot to accomplish in two days but with a great volunteer turn out it's possible. Come be a part of what God's doing in south Cape. We'll start working at 8 am on Saturday and again on Sunday at 1 pm.
Friday, May 9, 2008
Thursday update and Friday plans
Work will continue on Friday night at 6 pm. We hope to haul off broken concrete from the old driveway. We also plan on leveling the rock in the driveway, placing a retaining wall along the south side of the driveway and building forms to pour concrete for the driveway and sidewalks soon.
We would love to continue working on the siding and other projects around the house as well. If you're available to come out to help Friday night we would love to see you. If you have questions or need more information on how you can help please call our info line at 837-4047 or you can email us at info@thehouseGodbuilt.com.
Thursday, May 8, 2008
Wednesday update and Thursday plans
Wednesday, May 7, 2008
Tuesday update and Wednesday plans
There are plans for lots of work on Wednesday. The hardwood flooring will continue to be installed, doors and trim should be delivered and begin to be installed, painting touch-ups will continue, the electrical service panel will be placed, and the installation of electrical outlets, switches, and fixtures will start. Wednesday evening the cabinets will be delivered and their installation will begin. If weather permits there may be some progress on the siding.
We are continuing to move forward towards our dedication date of May 17th. Please consider coming out to be a part of this work. If you have any questions you can email us at info@thehouseGodbuilt.com or call our info line at 837-4047.
Tuesday, May 6, 2008
Monday update and Tuesday plans
Monday, May 5, 2008
Progress at THGB and help needed tonight
Sunday, May 4, 2008
Saturday progress and Sunday and Monday plans
Saturday, May 3, 2008
Next to last weekend to work at THGB
Friday, May 2, 2008
Weekend plans
We plan on working again Friday night, all day Saturday, and part of Sunday morning/early afternoon. We need to finish all painting and tile work soon so we will be ready to lay hardwood flooring next week. (Speaking of hardwood floors we need help to move it into the house on Monday evening.) We also will continue hanging siding this weekend and would like to finish that soon as well.
On Saturday we will plan to have heavy equipment working in the backyard to finish the sewer line. This will require taking down at least one tree. If anyone is available to help cut up the tree once it is on the ground that would be very helpful. We will also be grading the yard so that we can begin landscaping soon after the concrete has been poured in the basement floor and the driveway.
Please come help at any time that you can. Click here for times and days we will be working and please sign-up online or by calling us at 837-4047 so we can have a plan for the number of people that are wanting to help. An awesome lunch is being planned for Saturday so come prepared to work hard, have fun, and enjoy a good meal with old and new friends.
URGENT REQUEST: We need a dump truck driver to pick up a load of rock on Friday afternoon! We have a truck available to use. If you can help with this please call 986-3154. Thanks!
Thursday, May 1, 2008
Thursday work session planned
Wednesday, April 30, 2008
Wednesday night work session
Tuesday, April 29, 2008
Work continues tonight
Monday, April 28, 2008
Another weekend of work done
This week we hope to finish the interior painting, begin laying tile, finish the porch, and side the front of the house. It's an ambitious goal but should be achievable. We probably will also start painting the trim before it is installed next week.
Thursday, April 24, 2008
More painting Thursday night
This weekend we will continue painting. We need to complete the painting prior to Monday as the hardwood floors will be going in next week. Our plans are to also begin laying tile, complete the front porch, and begin siding the front of the house.
If you are available to help with any of these things please volunteer by signing up online or giving us a call on our info line at 837-4047. Lunch will be provided at noon on Saturday.
Wednesday, April 23, 2008
Painting begins!
We will likely have a painting crew in on Thursday evening as well. Check back here on the blog or at www.thehouseGodbuilt.volunteerhub.com for more information as it becomes available.
Tuesday, April 22, 2008
Weekend update and UPDATED plans for the week
This weekend we were able to make great progress on the siding. The north and back sides of the house are done and the south side of the house is done on the first level. We'll be able to finish this side and start the front later this week.
Monday, April 21, 2008
Work crew needed tonight
We will also be able to start masking off windows inside the house in preparation for primer and paint. If you would like to help with either of these activities you can sign-up online or if you have a last-minute opening in your schedule, just come on over. Hope to see you tonight.
Sunday, April 20, 2008
### Check back soon for plans for this week ##
You can help by praying for The House God Built! In addition to prayer, we also need volunteers who can help out during our work sessions. Times for these work sessions will be posted very soon. Check back Monday- we may have a Monday night work session and will likely have sessions on Tuesday, Wednesday, and Thursday in addition to our usual weekend times. Hope to see you at The House God Built this week!
Saturday, April 19, 2008
Rain Free (mostly) Saturday
Thursday, April 17, 2008
### CHANGE IN PLANS ###
Our plans for the weekend will include framing the front porch, continuing with siding, and laying tile. If you would like to help out with these activities we will work from 8-5 on Saturday and again from 1-5 on Sunday. If you have questions please give us a call on the info line at 837-4047 or email us at info@thehouseGodbuilt.com. As always, it helps us out if you can please sign-up online or give us a call if you think you can make it out to help.
We will update the blog with information about painting as soon as possible. We may need help during the week with taping off windows and other prep for painting once the drywall folks give us the ok. Please watch the blog for updates on how you can help out.
Sunday, April 13, 2008
Another weekend packed with progress
Saturday, April 12, 2008
Saturday update and upcoming plans
Friday, April 11, 2008
Siding, cement board, and lawn care - oh my
We have big plans for The House God Built this weekend and hope you can be a part of them! We will be hanging siding on the back and sides of the house as well as putting cement board down in the kitchen, dining room, laundry room, and bathrooms in preparation for laying tile soon. We also need to cut up a tree that fell during the ice storm and do some mowing/weedeating across the street where the construction trailer is parked. If you have them please bring tools appropriate for whichever of these jobs you would like to help with (i.e. hammer, extension ladder, scaffolding, chainsaw, mower, weedeater, etc.).
We can really use your help. If you have time to come over please give us a call at 837-4047 or sign-up online at www.thehouseGodbuilt.volunteerhub.com. Lunch will be provided on Saturday. We plan on working Saturday from 8 am to 5 pm and Sunday from 1 to 5 pm.
Monday, April 7, 2008
Siding continues
Monday, March 31, 2008
Siding starts going up!
Thursday, March 27, 2008
Siding begins!
For those who prefer working inside we have a few light tasks that can easily be done by inexperienced volunteers. We need to finish sanding over the screws in the drywall and do some clean-up in the house in preparation for the professional finishers. Once again, please let us know you are planning on coming by signing up online or giving us a call at 837-4047.
Wednesday, March 26, 2008
Spring Break work at THGB
Monday, March 24, 2008
Digging up the yard
Saturday, March 22, 2008
Final drywall (I think) and dirt work
If you can help come by today. Lunch is provided at noon.
Monday, March 17, 2008
Almost done with the drywall
We also are planning on working during the day on Friday and Saturday. We'll post more details about those days here on the blog very soon.
Drywall touch-up TONIGHT
If you have some time to help out tonight consider coming out to help. As always, you can register to volunteer online or by calling 837-4047.
Thursday, March 13, 2008
Plans for this weekend
Outside, we may try to finish the last bit of Tyvek and do a few other miscellaneous tasks.
If any of these things sound like fun we would love to see you this weekend but otherwise weather permitting we may be ready for a large group workday next Saturday.
Sunday, March 9, 2008
Drywall Blitz Continues Today
Saturday, March 8, 2008
Drywall Blitz Weekend
Friday, March 7, 2008
The weather outside is frightful...
At this point we are planning on working all day Saturday and Sunday afternoon. There has been some interest in a workday today and since most schools are closed and many businesses may follow that may be possible. If you are interested in working today please give us an email at info@thehouseGodbuilt.com or call 573-837-4047 and we'll try to put together a work session. Check back here on the blog for updates.
Monday, March 3, 2008
Progress update
We have set a goal of turning the house over to the professional drywall finishers by March 10th. This means that we have to finish hanging all of the remaining drywall this coming weekend. What remains is all of the perimeter walls (the inside of the exterior walls), both bathrooms, about half of the stairwell, and two closets. A lot of work for a few people but very manageable if we have groups of people that would be willing to lend a hand. A couple of experienced people are helpful but those who have never done this sort of work before can be very helpful as well. We’ll be getting the materials ready this week and should have everything in place for a big weekend. If you would like to help please sign-up online or call us at 837-4047 so we can be sure to have enough lunch available. If you have the following tools please bring them: T-square, tape measure, razor knife, and screw gun.
Thursday, February 28, 2008
Insulation is going in.
Sunday, February 24, 2008
More progress
Saturday, February 23, 2008
Drywall weekend continues!!
If you have time to help on Sunday please volunteer by signing up online or give us a call at 837-4047. If your small group would like to work on The House God Built as a Service project please contact us. We would love to have your help!
Friday, February 22, 2008
Drywall weekend
Bring a screwgun if you have one. We do have heat so the temperature in the house is comfortable while you're working.
Wednesday, February 20, 2008
Another milestone reached
Sunday, February 17, 2008
Awesome day at THGB
Check back on here frequently as we'll be posting our weekend plans soon.
More drywall work today
Friday, February 15, 2008
Finally time for drywall!!!
Wednesday, February 13, 2008
Still on hold for drywall
Tuesday, February 12, 2008
Unable to start drywall again tonight
Monday, February 11, 2008
Weather or not
Sunday, February 10, 2008
Drywall time!!
Join us at THGB this week
Today we'll also be pouring forms for the porch which will be framed later this week and digging the forms for the chimney. We'll start working at 1:00 today. If you have time to stop by we would love to have your help. Also, we will need help on Monday, Tuesday, and/or Wednesday evening (electrical inspection will determine when we can work) hanging drywall. Check back here for updated information on when this will occur or sign-up at www.thehouseGodbuilt.volunteerhub.com and we'll contact you.
Friday, February 8, 2008
Work for February 9 & 10
Saturday, February 2, 2008
Super Bowl Weekend update
Super Bowl Weekend at THGB
Monday, January 28, 2008
THGB progressing
Outside THGB we worked on digging forms for the front porch. Once those are inspected we'll be able to build the porch. As weather permits we'll begin siding the house also. Last week we got the fantastic news that the siding had been donated! We'll soon need people to hang it. Check back here regularly for news about when that will go up.
Many thanks go out to all who have donated materials or labor to this project! If you would like to sign-up to help check out http://www.thehousegodbuilt.volunteerhub.com/ or give us a call at 573-837-4047.